Boiler Permit FAQs
Contractors can request an inquiry with
The BSEED inspector/supervisor will review the facilities and repair plans to ensure proper application of the code requirements.
Annual: Required for installations and high-pressure repairs (internal and external), low pressure of more than 180,000 BTUs (internal and external), and all equipment.
Biennial: Required for pressure vessels that exceed 15 pounds per square inch (psi).
New Installation: Required for all boiler/pressure vessels
Repair Inspection: Required for all repairs to boilers or pressure vessels and piping.
Please note: The basic requirements are not limited to the above information, since an inspector can identify additional requirements in the inspection report.
The CSD-1 Standard applies to boilers more than 400,000 BTU/hr. to 12,500,000 BTU/hr.