Mayor Sheffield celebrates completion of massive $9.5M sidewalk replacement backlog of 6300 broken sidewalks
- All 6300 locations to be completed this year with less than 100 to go
- DPW started with occupied residential homes first and worked their way down
- City taking requests for 2027 construction season
- City Council approved $8M contract for Mayor's plan to clear entire backlog of requests that had accumulated over years
Mayor Mary Sheffield today celebrated with residents and staff after delivering on a promise she made earlier this year to clear out the entire backlog of 6300 locations in the sidewalk replacement program. Thousands of residents have requested sidewalk repair and have been waiting years for the broken sections of sidewalk in front of their homes to be replaced. Mayor Sheffield joined with happy residents as one of the last sidewalks was installed today with DPW contractors pouring new sidewalks along the 12000 block of East Outer Drive in the East English Village Neighborhood.
The program funded primarily through an $8 million allocation in Mayor Sheffield's budget, as well as $1.5 million in carryover funds from the previous budget. City Council approved an $8 million contract to allow most work to begin earlier this year.
"Sidewalks are a pivotal part of our neighborhoods," said Mayor Mary Sheffield. "Residents need to walk out of their doors and feel like improvements are happening in their neighborhood and all throughout the city. We are committed to investing in the entire city, not just our downtown areas."

“We have less than 100 locations left which will be completed by the end of the month delivering on Madam Mayor’s promise to finish all 6300 backlog locations by the end of this construction season,” said DPW Director Ron Brundidge.
"Our contractors worked at an aggressive pace to meet the mayor’s objective of having all of these locations completed by the end of this year," said Brundidge. "Before we began work, we delivered a notice to each home where work took place to let them know when work was to begin, what to expect and who to call with any questions. We are now taking requests for 2027 construction season."
Brundidge said that the process at each location took about a week to 10 days, depending on weather. First, the old sidewalk removed, then framing placed for the new flags. Once concrete was placed, it takes several days for it to properly cure and gain maximum strength before barricades are removed.
Brundidge said that a major aspect of this work is pedestrian safety.
"We see residents too often taking walks in the street to avoid uneven sidewalks," said Brundidge. "We hope that these repairs will encourage pedestrians to walk on the sidewalks, which are safely away from vehicle traffic."
Brundidge said the contracted work was closely monitored by inspectors from the City Engineering Division, ensuring the quality of the concrete, correctly poured and that it’s ADA compliant. He also added that any underground private sprinkler system, which are often around or near the sidewalk, that sustained damage during construction will be repaired or replaced by the city at no cost to the residents. The residents will have to fill out some paperwork to document the damage and make the claim.

DPW prioritized replacing damaged sidewalks in front of occupied residential homes first, before moving to side lots and other remaining locations.
The backlog consisted of locations reported before January 1, 2026. All sidewalk issues reported after January 1 of this year will be inspected and if qualifies then placed on the list for the 2027 construction season.
The Sidewalk Replacement Program is a free service for residents whose sidewalk has been damaged by city authorized work being done, tree roots that are between the curb and sidewalk, and other criteria that are required before a sidewalk can be replaced.